The new “Sunrise” City of Pullman park takes shape and pond starts to fill with water

Much progress the past two weeks, Most slopes have been hydro seeded and the mass grading is almost complete. Sunrise park is taking shape, the grading is completed and the hydro seeding is complete. Today the pathway construction starts around the pond. We have found several artisan springs that have been piped into the pond to fill it as you can see from the photos after a couple of days the pond is filling. the view to the east from the bike path is great see photos below. Next week the irrigation system and plantings start at the park.

Pond filling

Pond filling

View NE from park

View NE from park

view East from park

view East from park